5.6.2 System-Stopped/Cold Addition Workflow of the HDD/SSD


5.6.2 System-Stopped/Cold Addition Workflow of the HDD/SSD
Table 5-23 shows the workflow for system-stopped/cold addition of the HDD/SSD.
Table 5-23   System-Stopped/Cold Addition Procedure of the HDD/SSD
Work Order Task Reference
1 Powering off all physical partitions "9.5.2 Stopping All Physical Partitions"
2 Switching the mode switch on the OPNL to Service "2.3.2 OPNL Control Function"
3 Removing the power cords of all the SPARC M12-2/M12-2S units "9.8.2 Removing the Power Cords"
4 Removing the filler unit from the SPARC M12-2/M12-2S "15.3.2 Removing a Filler Unit"
5 Installing an HDD/SSD in the SPARC M12-2/M12-2S "15.4.1 Installing an HDD/SSD"
6 Connecting the power cords of all the SPARC M12-2/M12-2S units "10.1.1 Installing a Power Cord"
7 Diagnosing the SPARC M12-2/M12-2S with the added HDD/SSD "10.5.1 Diagnosing the SPARC M12 Hardware"
8 Confirming that there is no problem with the added HDD/SSD "10.5.3 Checking the FRU Status After Maintenance"
9 Switching the mode switch on the OPNL to Locked "2.3.2 OPNL Control Function"
10 Powering on all physical partitions "10.9.1 Starting the System With an XSCF Command"
11 Assigning the I/O resource to a logical domain "3.2 Operations and Commands Related to Logical Domain Configurations" in the Fujitsu SPARC M12 and Fujitsu M10/SPARC M10 Domain Configuration Guide