5.6.2 System-Stopped/Cold Addition Workflow of the HDD/SSD
5.6.2 System-Stopped/Cold Addition Workflow of the HDD/SSD
Before adding the HDD/SSD, see "Precautions for HDD/SSD addition" in "7.2 Precautions for FRU Expansion."
Table 5-23 shows the workflow for system-stopped/cold addition of the HDD/SSD.
Work Order | Task | Reference |
---|---|---|
1 | Powering off all physical partitions | "9.5.2 Stopping All Physical Partitions" |
2 | Switching the mode switch on the OPNL to Service | "2.3.2 OPNL Control Function" |
3 | Removing the power cords of all the SPARC M12-2/M12-2S units | "9.8.2 Removing the Power Cords" |
4 | Removing the filler unit from the SPARC M12-2/M12-2S | "15.3.2 Removing a Filler Unit" |
5 | Installing an HDD/SSD in the SPARC M12-2/M12-2S | "15.4.1 Installing an HDD/SSD" |
6 | Connecting the power cords of all the SPARC M12-2/M12-2S units | "10.1.1 Installing a Power Cord" |
7 | Diagnosing the SPARC M12-2/M12-2S with the added HDD/SSD | "10.5.1 Diagnosing the SPARC M12 Hardware" |
8 | Confirming that there is no problem with the added HDD/SSD | "10.5.3 Checking the FRU Status After Maintenance" |
9 | Switching the mode switch on the OPNL to Locked | "2.3.2 OPNL Control Function" |
10 | Powering on all physical partitions | "10.9.1 Starting the System With an XSCF Command" |
11 | Assigning the I/O resource to a logical domain | "3.2 Operations and Commands Related to Logical Domain Configurations" in the Fujitsu SPARC M12 and Fujitsu M10/SPARC M10 Domain Configuration Guide |