4.4.10 Inactive/Cold Replacement Workflow of Memory


4.4.10 Inactive/Cold Replacement Workflow of Memory
You can perform inactive/cold replacement of memory in the following configuration:
  1. Building block configuration where two or more physical partitions are operating
Table 4-38 shows the workflow for inactive/cold replacement of memory.
Table 4-38  Inactive/Cold Replacement Procedure of Memory
Work Order Task Reference
1 Checking the operating condition of the system "9.2.1 Checking the Operation Status of Physical Partitions and Logical Domains"
2 Confirming the memory to be replaced "8.2 Troubleshooting"
3 Checking the operation status of the SPARC M12-2S that houses the memory to be replaced "2.2.2 Checking Memory Information"
4 Powering off the physical partition containing the SPARC M12-2S that houses the memory requiring maintenance "9.5.1 Stopping a Specific Physical Partition"
5 Switching the mode switch on the OPNL to Service "2.3.2 OPNL Control Function"
6 Releasing the SPARC M12-2S requiring maintenance from the building block configuration "9.6.1 Releasing the SPARC M12-2S From the Building Block Configuration"
7 Placing the SPARC M12-2S requiring maintenance into the cold state, and removing memory from the SPARC M12-2S "17.4 Removing the CMU or Memory"
8 Installing memory in the SPARC M12-2S, and placing the SPARC M12-2S that required maintenance into the hot state "17.5 Installing the CMU and Memory"
9 Incorporating the SPARC M12-2S that required maintenance into the building block configuration "10.4.1 Incorporating the SPARC M12-2S Into a Building Block Configuration"
10 Diagnosing the SPARC M12-2S requiring maintenance (*1) "10.5.1 Diagnosing the SPARC M12 Hardware"
11 Diagnosing the XBU and crossbar cable of the SPARC M12-2S requiring maintenance "10.5.2 Diagnosing the XBU and Crossbar Cable"
12 Confirming that there is no problem with the replacement memory "10.5.3 Checking the FRU Status After Maintenance"
13 Switching the mode switch on the OPNL to Locked, and powering on the physical partition containing the SPARC M12-2S that has undergone maintenance "10.8 Powering on a Physical Partition"
14 Checking the operating condition of the system "9.2.1 Checking the Operation Status of Physical Partitions and Logical Domains"
*1 If the replaced memory was in a SPARC M12-2S with no PCIe cards mounted, no diagnosis is necessary (because diagnosis was performed in the previous step).