4.4.13 Inactive/Cold Replacement Workflow of the Crossbar Cable


4.4.13 Inactive/Cold Replacement Workflow of the Crossbar Cable
You can perform inactive/cold replacement of the crossbar cable in the following configuration:
  1. Building block configuration where two or more physical partitions are operating
Table 4-41 shows the workflow for inactive/cold replacement of the crossbar cable.
Table 4-41  Inactive/Cold Replacement Procedure of the Crossbar Cable
Work Order Task Reference
1 Checking the operating condition of the system "9.2.1 Checking the Operation Status of Physical Partitions and Logical Domains"
2 Confirming the crossbar cable to be replaced "8.2 Troubleshooting"
3 Checking the operation status of the SPARC M12-2S that is connected to the crossbar cable to be replaced "10.5.2 Diagnosing the XBU and Crossbar Cable"
4 Powering off the physical partition containing the SPARC M12-2S that is connected to the crossbar cable requiring maintenance "9.5.1 Stopping a Specific Physical Partition"
5 Switching the mode switch on the OPNL to Service "2.3.2 OPNL Control Function"
6 Releasing the SPARC M12-2S requiring maintenance from the building block configuration "9.6.1 Releasing the SPARC M12-2S From the Building Block Configuration"
7 Placing the SPARC M12-2S requiring maintenance into the cold state, and removing the crossbar cable from the SPARC M12-2S "19.3 Removing the Crossbar Cable"
8 Installing the crossbar cable on the SPARC M12-2S, and placing the SPARC M12-2S that required maintenance into the hot state "19.4 Installing the Crossbar Cable"
9 Incorporating the SPARC M12-2S that required maintenance into the building block configuration "10.4.1 Incorporating the SPARC M12-2S Into a Building Block Configuration"
10 Diagnosing the crossbar cable "10.5.2 Diagnosing the XBU and Crossbar Cable"
11 Confirming that there is no problem with the replacement crossbar cable "10.5.3 Checking the FRU Status After Maintenance"
12 Switching the mode switch on the OPNL to Locked, and powering on the physical partition containing the SPARC M12-2S that has undergone maintenance "10.8 Powering on a Physical Partition"
13 Checking the operating condition of the system "9.2.1 Checking the Operation Status of Physical Partitions and Logical Domains"