You can perform inactive/cold replacement of the XSCF BB control cable in the following configuration:
  1. Building block configuration where two or more physical partitions are operating
Table 4-45 shows the workflow for inactive/cold replacement of the XSCF BB control cable.
Table 4-45  Inactive/Cold Replacement Procedure of the XSCF BB Control Cable
Work Order Task Reference
1 Checking the operating condition of the system "9.2.1 Checking the Operation Status of Physical Partitions and Logical Domains"
2 Confirming the XSCF BB control cable to be replaced "8.2 Troubleshooting"
3 Checking the operation status of the SPARC M12-2S connected to the XSCF BB control cable to be replaced "8.1.2 Checking Hardware"
4 Powering off the physical partition containing the SPARC M12-2S connected to the XSCF BB control cable requiring maintenance "9.5.1 Stopping a Specific Physical Partition"
5 Switching the mode switch on the OPNL to Service "2.3.2 OPNL Control Function"
6 Releasing the SPARC M12-2S requiring maintenance from the building block configuration "9.6.1 Releasing the SPARC M12-2S From the Building Block Configuration"
7 Placing the SPARC M12-2S requiring maintenance into the cold state, and removing the XSCF BB control cable from the SPARC M12-2S "22.3 Removing the XSCF BB Control Cable"
8 Installing the XSCF BB control cable, which is a maintenance part, on the SPARC M12-2S, and placing the SPARC M12-2S that required maintenance into the hot state "22.4 Installing the XSCF BB Control Cable"
9 Incorporating the SPARC M12-2S that required maintenance into the building block configuration "10.4.1 Incorporating the SPARC M12-2S Into a Building Block Configuration"
10 Confirming that there is no problem with the replacement XSCF BB control cable "10.5.3 Checking the FRU Status After Maintenance"
11 Switching the mode switch on the OPNL to Locked, and powering on the physical partition containing the SPARC M12-2S that has undergone maintenance "10.8 Powering on a Physical Partition"