  9. D.2 From Installation of a Configuration with Direct Connections between Chassis to Initial Diagnosis

D.2 From Installation of a Configuration with Direct Connections between Chassis to Initial Diagnosis


D.2 From Installation of a Configuration with Direct Connections between Chassis to Initial Diagnosis
Table D-2  Work descriptions and references (direct connections between chassis)
Work description Check Checked by Installation Guide reference
1. Before installing the system, check the safety precautions, system specifications, and necessary conditions for installation. [   ]   "Chapter 2 Planning and Preparing for System Installation"
2. Prepare the necessary tools/information for installation. [   ]   "3.1 Preparing the Necessary Tools/Information for Installation"
3. Confirm the delivered components.
If the BB configuration is set up at the delivered site, check the BB-ID specified on the operation panel. (*1)
[   ]   "3.2.1 Confirming the delivered components of the SPARC M10-4S"
  [   ]   "3.2.2 Confirming the delivered components of the PCI expansion unit"
4. Install the rack. [   ]   "2.4.1 Mounting conditions for general racks"
"3.3 Installing a Rack"
5. Mount the SPARC M10-4S in the rack. [   ]   "3.4.1 Mounting the SPARC M10-4S in a rack"
6. If there is a PCI expansion unit, mount it in the rack. [   ]   "3.4.2 Mounting the PCI expansion unit in a rack"
7. After mounting the SPARC M10-4S, confirm the complete contact (complete engagement) of the internal disk, fan unit, and PCI cassettes.
At this time, confirm that the PCI cassette lever is locked.
[   ]    
8. If there are optional components, mount them on the SPARC M10-4S and the PCI expansion unit.
(For details, see the service manual.)
[   ]   "3.5.1 Mounting optional components in the SPARC M10-4S"
"3.5.2 Mounting optional components in the PCI expansion unit"

In the Fujitsu M10-4/Fujitsu M10-4S/SPARC M10-4/SPARC M10-4S Service Manual:
"Chapter 8 Maintaining the PCI Express Cards"
"Chapter 9 Maintaining the CPU Memory Unit/Memory"
"Chapter 10 Maintaining the Internal Disks"
9. Check the identification ID of each SPARC M10-4S. [   ]   "Chapter 4 Configuring Building Block Connections"
"4.1 Setting the ID (BB-ID) Identifying a Chassis"
10. Connect the XSCF BB control cable and the XSCF Dual control cable to each SPARC M10-4S.     "4.2.1 Connecting XSCF cables"
11. Connect the crossbar cables (electrical) to each SPARC M10-4S.     "4.2.2 Connecting crossbar cables"
12. Connect serial cables (*2), LAN cables, and power cords to the SPARC M10-4S. [   ]   "5.1 Connecting Cables to the SPARC M10-4S"
13. Connect the link cable and management cable to the PCI expansion unit and the SPARC M10-4S.
Attach the core to the power cord, and connect the power cord to the PCI expansion unit.
[   ]   "5.2 Connecting Cables to the PCI Expansion Unit"
14. Store the cables connected to the SPARC M10-4S in the rack. Check the rack in use, and store them in a way that is appropriate for the rack. [   ]   "5.4 Storing Cables"
"5.4.1 Rack with a width of 700 mm (27.6 in.)"
"5.4.2 Rack with a width of 600 mm (23.6 in.)"
15. Connect the system management terminal to the SPARC M10-4S that is the master XSCF. [   ]   "6.1 Connecting the System Management Terminal to the Chassis"
16. Check the BB-ID setting. [   ]   "6.2.1 Checking the BB-ID setting"
17. Turn on the input power, and check the status from the LED display on the XSCF unit. [   ]   "6.2.2 Turning on the input power and starting the XSCF"
18. Log in to the master XSCF. [   ]   "6.3 Logging In to the XSCF"
19. Check the XCP version. [   ]   "6.4 Checking the XCP Version"
20. Set the altitude. [   ]   "6.5 Checking the Altitude Setting"
 * There is no need to set the altitude if it is unknown.
21. Set the time. [   ]   "6.6 Checking the Time Setting"
22. Perform the initial diagnosis test. [   ]   "6.7 Performing a Diagnosis Test"
 The probe-scsi-all command and the show-devs command are displayed as command options in the diagnosis test.

 Confirm that the installed disk capacity and number of units, and the installation position and device name of the PCI Express card are correct.
23. Confirm that that each component is normally recognized, and no errors occur. [   ]   "6.8 Checking the Component Status"
*1 Be sure to check the BB-ID specified on the operation panel on the SPARC M10-4S before connecting the SPARC M10-4S with the BB configuration and powering on at the delivered site. The BB-ID will not be updated if only the BB-ID on the operation panel is changed. Be sure to connect the SPARC M10-4S with the BB-ID specified on the operation panel.
*2 Connect the serial cables to the serial ports of the SPARC M10-4S operating as the master XSCF.