2.2 Items Requiring Confirmation Before Installation
2.2 Items Requiring Confirmation Before Installation
This section describes the items that you need to confirm before installing the SPARC M12-2. Before starting installation work, confirm that the requirements in Table 2-1 have been met.
Check Item | Check Column | |
---|---|---|
System configuration | - Has the system configuration been determined? |
|
- Has the required rack space been confirmed? |
||
- Has the number of racks been decided? |
||
Training | - Have the system administrator and operators attended the required training courses? |
|
Installation location | - Has the system installation location been determined? |
|
- Does the placement of each chassis meet the service area requirements? |
||
- Have the chassis been placed so that their air intakes do not take in exhaust from other equipment? |
||
- Have the rack installation requirements been met? |
||
Access route | - Has the access route for the rack been secured? |
|
Environmental conditions | - Does the installation location meet the temperature and humidity conditions? |
|
- Can the environmental conditions at the installation location be adequately maintained and controlled? |
||
- Have security measures been established for the installation location? |
||
- Does the installation location have sufficient fire extinguishing equipment? |
||
Power supply facilities | - Do you know the voltage available for the racks where the SPARC M12-2, the PCI expansion unit, and peripherals will be mounted? |
|
- Are the power supply facilities sufficient for the SPARC M12-2, the PCI expansion unit, monitors, and peripherals? |
||
- Are the power supply facilities within an appropriate distance from the racks? |
||
Network specifications | - Do you have the necessary information for network connections? |
|
CPU Activation | - Has the amount of resources to be used during initial installation been determined? |
|
- Have the required CPU Activations been ordered? |