1.1 Workflow for the SPARC M12-1


1.1 Workflow for the SPARC M12-1
The SPARC M12-1 is a 1U-size chassis with one CPU (six cores). This compact model combines a space-saving design and high performance.
This section describes the workflow from installing the SPARC M12-1 and PCI expansion unit to making the initial system settings. The PCI expansion unit will be connected with optional components to the SPARC M12-1.
The initial system settings are implemented before system startup, and they include the XSCF setup and CPU Activation setting. Skip the steps for the PCI expansion unit if it is not to be installed.

By clicking a reference enclosed in " " to display a section, you can see the details of the respective step. Italic font is used to indicate the name of a reference manual other than this manual.
Table 1-1  Workflow for the SPARC M12-1
Step (Work Time (*1)) Work Description Reference  
Installation work (approx. 36 minutes (*2))
1 Check the latest information available in the Fujitsu SPARC M12 Product Notes. Fujitsu SPARC M12 Product Notes Required
2 Before installing the system, check the safety precautions, system specifications, and necessary conditions for installation. "Chapter 2 Planning and Preparing for System Installation" Required
3 Prepare the necessary tools/information for installation. "3.1 Preparing the Necessary Tools/Information for Installation" Required
4 Confirm the delivered components. "3.2.1 Confirming the Delivered Components of the SPARC M12-1" Required
    "3.2.2 Confirming the Delivered Components of the PCI Expansion Unit" Optional
5 Install the rack. See the manual for each rack.
"3.3 Confirming the Rack"
Required
6 Mount the SPARC M12-1 in the rack. "3.4.1 Mounting the SPARC M12-1 in a Rack" Required
7 If there is a PCI expansion unit, mount it in the rack. "3.4.2 Mounting the PCI Expansion Unit in a Rack" Optional
8 If there are optional components, mount them in the SPARC M12-1 or the PCI expansion unit. "3.5.1 Mounting Optional Components in the SPARC M12-1" Optional (*3)
    "3.5.2 Mounting Optional Components in the PCI Expansion Unit" Optional (*3)
9 Connect serial cables and LAN cables to the SPARC M12-1. Attach the core to the power cord, and connect the power cord to the power supply unit. "4.1 Connecting Cables to the SPARC M12-1" Required
10 If there is a PCI expansion unit, connect the link cable and management cable to the PCI expansion unit.
Attach the core to the power cord, and connect the power cord to the power supply unit.
"4.2 Connecting Cables to the PCI Expansion Unit" Optional (*4)
Initial diagnosis (approx. 30 minutes)
11 Connect the system management terminal to the SPARC M12-1, and turn on the input power. "5.1 Connecting the System Management Terminal to the Chassis"
"5.2 Turning On the Input Power and Starting the XSCF"
Required
12 Log in to the XSCF of the SPARC M12-1, and check the firmware version number, altitude setting, and time setting. "5.3 Logging In to the XSCF"
"5.4 Checking the XCP Version"
"5.5 Checking the Altitude Setting"
"5.6 Setting the Time"
Required
13 Perform the initial diagnosis test on the hardware. "5.7 Performing a Diagnosis Test" Required
14 Check the status of mounted components. "5.8 Checking the Component Status" Required
Initial system settings (approx. 50 minutes)
15 Set the password policy. "6.1 Setting the Password Policy" Required
16 Set a user account and password. "6.2 Setting a User Account and Password" Required
17 Configure the telnet or SSH service. "6.3 Configuring the Telnet/SSH Service" Required
18 Configure the HTTPS service. "6.4 Configuring the HTTPS Service" Required
19 Configure the XSCF network. "6.5 Configuring the XSCF Network" Required
20 When duplicating memory, configure memory mirroring. "6.6 Configuring Memory Mirroring" Optional
21 Create a PPAR configuration list. "6.7 Creating a PPAR Configuration List" Optional (*5)
22 Assign the SPARC M12-1 (system board) to a physical partition. "6.8 Checking the Physical Partition (PPAR) Status" Optional
23 Clear the difference between the system time and physical partition (PPAR) time. "6.9 Synchronizing the Physical Partition (PPAR) Time and XSCF Time" Required
24 Register a CPU Activation key with the XSCF. "6.10 Registering a CPU Activation Key" Required (*6)
25 Assign CPU core resources to the physical partition. "6.11 Assigning CPU Core Resources" Required
26 Confirm the start/stop of the physical partition and the connection of the console. "6.12 Starting/Stopping the System (PPAR)" Required
27 Either use the preinstalled Oracle Solaris as is or reinstall it. (Note)    
28 Save XSCF setting information and logical domain configuration information. "6.14 Saving Configuration Information" Required (*7)
*1 Average work time
*2 Time required for mounting optional components and installing the PCI expansion unit is not included.
*3 If the optional components are ordered together with the SPARC M12-1, they are shipped mounted to the SPARC M12-1. If the PCI expansion unit is also ordered, the optional components (memory, internal storage (HDD/SSD), PCIe card) are shipped mounted to the PCI expansion unit.
*4 In Japan, the link card is shipped mounted to the SPARC M12-1. Outside Japan, the link card is packed and shipped together with the PCI expansion unit.
*5 The physical partition configuration information is already set.
*6 One CD-ROM disk containing a CPU Activation certificate is provided with the system. The CPU Activation key may be registered with the system.
*7 If you have started Oracle Solaris and changed the configuration of a logical domain, save the logical domain configuration.
Note - The SPARC M12 systems have Oracle Solaris preinstalled. According to the purpose, either use the preinstalled Oracle Solaris as is or reinstall it.
To reinstall Oracle Solaris, see the Fujitsu SPARC M12 Product Notes for the latest information on the supported Oracle Solaris versions, Oracle VM Server for SPARC versions, and SRUs.